flowchart TB A["ReadMe Documentation"] B["Guides"] C["API Reference"] D["Editor UI"] E["OpenAPI Spec"] F["Manual Editor"] G["Slash Commands"] H["Mermaid Diagrams"] I["Other Blocks"] A --> B A --> C B --> D C --> E C --> F D --> G G --> H G --> I %% mermaid-flow:pos A=60,60 B=60,260 C=170,260 D=60,460 E=170,460 F=280,460 G=60,660 H=60,860 I=170,860
📋 Meeting Notes — May 20, 2026
Meeting: NovaPay Q3 Launch Sync
Duration: 45 min
Facilitator: Mohammed
Agenda
- Timeline review
- Beta partner status
- Design refresh update
- Engineering blockers
Discussion Notes
Timeline Review
Sara confirmed the core SDK is on track for June 15 freeze. The main risk is the payment processor contract — without test credentials, QA can’t run full end-to-end scenarios. Mohammed to chase legal today.
Beta Partner Status
Priya has 6 confirmed design partners out of the target 10:
- Acme Retail (e-commerce)
- Bolt Coffee (F&B)
- KidzLearn (edtech)
- MedBook (healthcare — HIPAA implications, legal reviewing)
- RideAlong (mobility)
- StyleHaven (fashion)
Still in conversation: 3 more prospects (NDA not signed). One dropped out (went with a competitor).
Action Item
Priya to send follow-up emails to the 3 prospects by May 24.
Design Refresh Update
Liam presented 3 new color palette options. Team voted for Palette B (deep teal + warm white). Brand guidelines will be ready by June 5. Logo finalization needs one more round with the CEO.
Risk
If logo isn’t final by June 5, the docs site timeline slips. Sara flagged this as a hard dependency.
Engineering Blockers
- P1 Bug — iOS crash on 3DS authentication: Root cause found, fix in review, ETA May 25.
- React Native bridge performance: ~200ms overhead on Android. Sara says acceptable for launch, will optimize in v1.1.
- Webhook retry logic: Not implemented yet. Pushed to v1.1 per scope agreement.
Decisions Made
| Decision | Owner |
|---|---|
| Biometric auth is opt-in at launch | Sara |
| Apple Pay deferred to v1.1 | Mohammed |
| Palette B selected for brand refresh | Liam |
| Webhook retries deferred to v1.1 | Mohammed |
Action Items
- Mohammed — Chase legal on processor contract by EOD May 20
- Priya — Follow up with 3 prospects by May 24
- Liam — Share brand guidelines draft by June 5
- Sara — Confirm P1 iOS fix merged by May 25
- Mohammed — Schedule CEO logo review before May 28
Next Meeting
Date: June 3, 2026
Topic: Beta launch readiness check